8.3.3.6 Task list
Each BSCW user has a personal task list that contains all tasks that the
user is supposed to carry out as contractor. The task list is accessed via
or the tasks icon in the instant
access bar
.
When a task is first requested, it appears in the task list of all task
contractors assigned. When a user loses the contractor role, e.g., by
deleting or rejecting a task, it disappears from the user’s task
list.
The task list also contains project processes for which the user is responsible (see 8.1) and flow folders in which the user is to carry out the current task (see 8.2).